West 50th Avenue, West 51st Avenue and Dunbar Street water main reconstruction project
City crews have completed the reconstruction of the water main along West 50th Avenue, West 51st Avenue and Dunbar Street.
Project details
Location and expected duration
- 6500-6600 blk Dunbar Street (from West 49th Avenue to West 51st Avenue)
- Start: April 08, 2014
- End: May 23, 2014
- 3600-3800 blk West 50th Avenue (from Dunbar Street to Wallace Street)
- Start: May 12, 2014
- End: June 2014
- 3600-3800 blk West 51st Avenue (from Dunbar Street to Wallace Street)
- Start: November 2014
- End: December 2014
Hours of work
- Monday to Friday, 7:00am to 3:30pm (may include weekend work)
Status
- Completed
Impacts to traffic, parking and residents
Traffic in West 50th Avenue, West 51st Avenue and Dunbar Street adjacent to the project area will be reduced to single lane alternating. Flaggers and signages will be used to direct traffic.
Access to residents will be maintained at all times. Access to the Musqueam Golf Course will be maintained at all times.
Local parking may also be affected by the presence of our work trailers and construction equipment.
If you are expecting deliveries or need to access to your parking, please contact us and our crews will do their best to accommodate you.
How this project will improve the city
This project will improve the condition of the water main system in this neighbourhood. Watermain capacity is also being increased to better serve the community.