Timeline

Here is our progress and planned steps to rebuild the playground.

  • Fall 2016

    Project begins

  • Dec 2016

    Open house about park upgrades

  • Winter 2017

    Design development

  • We are here
  • Spring 2017

    Open house about proposed concepts

  • Summer 2017

    Detailed design

  • Fall 2017

    Playground and staircase construction begins

  • Jan 2018

    Pump station construction begins

  • Dec 2018

    Pump station completed

Past updates

Winter 2016

We asked you to provide feedback on possible options for upgrading the park at a public open house held on December 8, 2016, and in an online questionnaire, which ran from December 8, 2016, to January 6, 2017. A total of 157 respondents completed the questionnaire.

The consultation summary below provides an overview of the feedback from community members on a number of options for the China Creek North Park upgrades. Thank you to everyone who provided feedback!

Contact the project team

Lehran Hache
Landscape Designer

lehran.hache@vancouver.ca